By definition, the predecessor is the first task; it controls the start or end date for all related successor tasks. The successor, by contrast, is the task whose start or end date is controlled by the predecessor. A dependency is the relationship between predecessor and successor tasks.Click to see full answer. Then, what is a successor in MS Project?In project management a successor is an activity that follows another activity – not in the chronological sense but according to their dependency to each other. A successor activity can have several direct predecessor activities.Likewise, what is a predecessor and successor? “Predecessor” means an entity that is replaced by a successor and includes any predecessors of the predecessor. “Successor” means an entity that has replaced a predecessor by acquiring the assets and carrying out the affairs of the predecessor under a new name (often through acquisition or merger). Correspondingly, how do I view predecessors and successors in MS Project? While in Gantt chart view, you can choose Details and then show the Task form at the bottom. In the task form you can choose(right click) to show predecessors and successors. As you scroll through the tasks in the Gantt chart, the corresponding predecessor and successor tasks shows up in the Task form.What is a successor task?Predecessor tasks come first and successor tasks follow. Predecessor tasks refer to tasks that must be completed or at least begin before another task can start. Successor tasks are those that follow the predecessor.